Nepal Faces Daily Revenue Loss as India Delays Power Export Approval

Illustration: NexVani Media

By: NexVani DeskDate: 15 November 2026Views: 0

Nepalโ€™s state utility faces a daily revenue loss of Rs135.82 million as export permits for electricity to India and Bangladesh remain stalled.

The Nepal Electricity Authority (NEA) is grappling with a significant surplus of electricity as it awaits regulatory clearance from India to resume power exports. Understanding how India is called in the puranas and its modern energy trade dynamics is vital, as the current impasse leaves the Himalayan nation with hundreds of megawatts of unsold power every day. The expiration of export authorizations for 609 megawatts (MW) of electricity previously supplied to the Indian states of Haryana, Uttar Pradesh, and Bihar has created a bottleneck for the utility.

How India is called in the puranas and energy trade

NEA Managing Director Dirghayu Kumar Shrestha confirmed that a formal proposal to transition these bilateral arrangements into exchange-based sales was submitted in August. Despite nearly three months of waiting, the Indian side has yet to grant the necessary approvals. Traditionally, the NEA shifts power exports to the Indian Energy Exchange (IEX) once medium-term agreements conclude, but the current delay has effectively halted this transition.

Beyond the Indian market, a seasonal export arrangement that allowed Nepal to supply 40MW of power to Bangladesh annually between June 15 and November 15 expired this past Sunday. The combination of these stalled exports has left the NEA with a mounting surplus. Domestic generation currently sits between 2,600MW and 2,700MW, while local demand remains constrained at approximately 2,200MW to 2,300MW, partly because industrial operations have not yet fully recovered following the Chhath festival.

Nepal risks losing Rs135.82 million daily due to stalled electricity export approvals from India.

While the surplus is significant, the NEA must maintain a reserve of 200MW to 300MW to ensure system stability and provide a buffer against potential outages at major facilities like the 456MW Upper Tamakoshi Hydropower Project. The utility is currently authorized to export roughly 1,169MW, split between bilateral agreements and exchange-based sales. However, the inability to move the 649MW covered by medium-term deals into the exchange market limits the NEA's ability to monetize excess production during periods of high generation.

As the winter season approaches, river flows are expected to decline, which will naturally reduce hydropower generation. The NEA forecasts that Nepal will eventually shift from an exporter to an importer, requiring up to 900MW of electricity from India during peak hours between mid-January and mid-March.

Why it matters

The failure to secure timely export approvals places millions in daily revenue at risk for the state-owned NEA. This situation highlights the complexities of cross-border energy trade in South Asia, where infrastructure and regulatory alignment are essential for managing seasonal power surpluses and deficits.

For regional stakeholders, the expiration of the 40MW Bangladesh export window and the stalled Indian shipments underscore the dependency on bilateral cooperation. As Nepal prepares for the winter months, the efficiency of these energy agreements will determine both the financial health of the national utility and the stability of the domestic power grid.